Renovation and on-site PREFABRICATION

An existing house has been restored from the basement. On its foundation a new building with 200 m² of space was built on two floors.

Accurate and exact execution plans are important for load bearing dry construction. These documents must be verified by a structural engineer. For the building, 1’300 meters of Cocoon lightweight steel frame Transformer profiles were cut according to the plan, assembled and delivered to the construction site.

On-site, the bearing walls and ceilings were connected into frames.
The planking of the profiles is the same as the usual dry construction method.

Documentation: Project report house Russo in German

Photos: Knauf AG

 

 

 

 